South Africa: South Gauteng High Court, Johannesburg Support SAFLII

You are here:  SAFLII >> Databases >> South Africa: South Gauteng High Court, Johannesburg >> 2018 >> [2018] ZAGPJHC 423

| Noteup | LawCite

Coalcor Mining (Pty) Ltd v Islandsite Investments One Hundred and Eighty (Pty) Ltd and Others (14359/18) [2018] ZAGPJHC 423 (14 June 2018)

Download original files

PDF format

RTF format


REPUBLIC OF SOUTH AFRICA

IN THE HIGH COURT OF SOUTH AFRICA

GAUTENG LOCAL DIVISION, JOHANNESBURG

CASE NO: 14359/18

In the matter between:

COALCOR MINING (PTY) LTD                                                                         APPLICANT

And

ISLANDSITE INVESTMENTS ONE HUNDRED                                    1ST RESPONDENT

AND EIGHTY (PTY) LTD

KURT ROBERT KNOOP N.O                                                                2ND RESPONDENT

JOHAN LOUIS KLOPPER N.O                                                             3RD RESPONDENT


JUDGMENT


KEIGHTLEY, J

1. The applicant, Coalcor Mining (Pty) Ltd (Coalcor), seeks an order restoring to it certain underground mining equipment.  It bases its application on the rei vindicatio.

2. The application was launched on what Coalcor describes as being a “semi-urgent basis”: the application was instituted on 12 April 2018, and was enrolled for hearing on 8 May 2018, with the respondents being afforded until 25 April to file an answering affidavit.  As matters turned out, the application did not proceed on 8 May 2018, with the costs of those proceedings being reserved.  It was then set down again for hearing on 15 May 2018.  The matter served before me in the urgent court, and I directed the parties to seek a special allocation of the matter from the Deputy Judge President.  He allocated 24 May 2018 as the date for the hearing, and the matter came before me once again.

3. The first respondent is Islandsite Investments Onehundred and Eighty (Pty) Ltd (Islandsite).  It was placed in business rescue on 19 February 2018.  The second and third respondents are the business rescue practitioners appointed in respect of Islandsite.  Islandsite forms part of the Oakbay stable of companies, several of which are under business rescue.

4. The dispute has its origins in a Sale of Equipment and Mining Contract Takeover Agreement (the agreement) entered into between Coalcor and Islandsite in 2016.  The agreement encompassed the sale of Coalcor’s mining equipment, and a cession by Coalcor to Islandsite of its rights and assignment of its obligations under an underground mining contract pertaining to the Boschmanspoort Mine.  The total contract price under the agreement was R240 million, payable in instalments, with the first instalment of R50 million falling due on 1 November 2016, and the final instalment of R90 million falling due on 1 February 2017.

5. The agreement contained further relevant provisions:

5.1. In terms of clause 12.1, ownership of the equipment remained vested in Coalcor pending full payment of the contract price and any other amounts due.

5.2. In terms of clause 12.2.2, upon payment of any instalment becoming overdue Islandsite was obliged immediately to cease the use of the equipment.

5.3. Clause 13 dealt with a breach of the agreement by Islandsite.  It provided, in relevant part that:

13.1.1 (should) the Purchaser fail to pay any amount or amounts payable to the Seller … properly and on due date and fail to remedy the breach within 14 days of written notice requiring it to do so; or

13.1.2 (should) the Purchaser be placed under … business rescue; or …..

13.2.1 the Seller shall then have the right, without prejudice to any other rights which may be available to it, to cancel the agreement forthwith without further demand and to retain all payments already made … as rouwkoop.

13.2.3 the Seller may, without prejudice to it other rights demand immediate delivery of the equipment from the Purchaser who undertakes to immediately deliver the equipment to the seller in the same or better condition and state of repair as it was on the effective date.”

6. Clause 14 dealt with dispute resolution.  It provided that:

Any dispute arising from or in connection with this agreement will be finally resolved by arbitration.”

7. Clause 14.6 contained a proviso to the arbitration clause in that it provided that:

Nothing contained in this clause 14 shall prohibit a Party from approaching any court of competent jurisdiction for urgent interim or other relief pending determination of the dispute by arbitration.

8. It is common cause that Islandsite defaulted on its payment obligations under the agreement, with the last payment, of R40 million, being made on 4 May 2017.  The remaining balance under the agreement was R25 million.  It is common cause that 90% of the contract price has been paid.  Coalcor did not seek to enforce its rights under clause 13.1.1 at that stage.  However, when Islandsite was placed in business rescue on 19 February 2018, Coalcor decided to act on its rights under clause 13.1.2, read with 13.2.1.  It sent a letter of cancellation to the business rescue practitioners on 8 March 2018, and demanded the return of the equipment.

9. When Coalcor did not receive a satisfactory response, it sent another letter, on 22 March, again requesting the return of the equipment, and warning that if this did not happen by 28 March 2018, Coalcor would institute court proceedings.  As I have already indicated, it instituted these proceedings some two weeks later.  It cited the alleged current state of disrepair of the equipment, and the continued use thereof by Islandsite as exposing it to irreparable harm if its right to vindicate the equipment was not dealt with urgently.

10. I should add that by the time the application was launched, the business rescue practitioners had filed a provisional business rescue plan. This was on 3 April 2018.  It reflected the equipment as being an asset of Islandsite, and proposed the continuation of business activities, presumably involving the continued use of the mining equipment.  The plan also reflected Coalcor as a trade creditor, and estimated that under the business rescue plan, as a trade creditor it would be paid 100 cents in the Rand within the next six to nine months.  An amended plan, with no material amendments as regards Coalcor’s situation, was adopted at a meeting convened in terms of s152 of the Companies Act on 26 April 2018.  Coalcor has elected not to participate in the business rescue proceedings and did not approve the plan.

11. I have already briefly outlined the litigation history of this matter.  It is relevant to record further that the respondents filed an answering affidavit on 3 May 2018, shortly before the first set down date for the hearing.  It raised two main points of contention: the alleged urgency of the matter; and the contention that the cancellation by Coalcor under clause 13.2.1, and the enforcement of its rights under clause 13.2.2 are contra bonis mores, given the fact that Islandsite had paid 90% of the contract price and that the cancellation and demand for return of the equipment meant that it would lose all the money it had already paid, as well as the equipment.  This, contended the respondents, was particularly contrary to public policy given that Islandsite was under business rescue, and the cancellation would prejudice these proceedings.

12. A replying affidavit was filed by Coalcor on 7 May 2018.  The respondents subsequently (on 16 May 2018) filed a counter-application in which it sought formal relief in the form of a declaration that the cancellation of the agreement on 8 March 2018 was of no force and effect on the basis that it was offensive to public policy and inimical to the values enshrined in the Constitution and hence unenforceable.

13.  After the matter was referred by me for special allocation, further developments took place.  The respondents brought new counsel on board (as their previous counsel was not available for the allocated date of the hearing).  On his advice, the respondents filed an application for leave to file a supplementary affidavit.  The express purpose of the supplementary affidavit was to raise a plea in abatement, based on an arbitration defence arising out of clause 14 of the agreement.  This application was filed on the eve of the hearing before me.  Coalcor did not object to the application, and I granted leave to file the supplementary affidavit.  This brought into play the arbitration defence raised by the respondents, the gist of which is that any dispute between the parties arising out of the agreement and involving the grant of final relief cannot proceed before a court, and can only proceed by way of arbitration.  The necessary consequence of this defence, should it succeed, is that these court proceedings must be stayed pending the finalisation of arbitration proceedings.

14. By the time the matter was heard, the identified issues in dispute were the following:

14.1. The question of urgency.

14.2. The arbitration defence.

14.3. The counter-application (and hence the validity of the cancellation of the agreement).

14.4. The question of whether section 133(1) of the Companies Act precluded Coalcor’s resort to litigation.  This section provides that no legal proceedings may, without, among others, the consent of the court, be instituted in relation to any property “lawfully in possession” of a company under business rescue.  The issue at hand was whether, for purposes of this section, the lawfulness of possession is determined at the time that business rescue is commenced, or at the time that the litigation in question is instituted.  The respondents contended for the former interpretation:  in other words, when Islandsite went into business rescue, Coalcor had not yet cancelled the agreement and its possession was, and for purposes of s133(1) remained, lawful, and thus immune from litigation based on the rei vindicatio without the court’s consent.  Coalcor contended for the latter interpretation: in other words, Islandsite’s possession became unlawful on cancellation and thus was unlawful at the time Coalcor instituted its rei vindicatio.  This means s133 did not preclude its application to court.  Even if it did, Coalcor requested the court to consent to the litigation.

14.5. An issue around the application of s152(4) of the Companies Act was dealt with by Coalcor in its oral submissions to the court, but the need to determine this issue fell away when the respondents indicated that they would not press the issue.  The respondents accordingly accepted that the business rescue plan was not binding on Coalcor as a trade creditor.

15. The two preliminary issues that arise for consideration are those of urgency and the arbitration defence.  The section 133 issue is also, in a sense, preliminary, but I do not need to consider it if I find in favour of the respondents in respect of either the issue of urgency, or the arbitration defence.  If, on the other hand, Coalcor is good on the three preliminary points identified earlier, everything will depend on the outcome of the counter-application: Coalcor accepts that if its cancellation of the contract was invalid, it cannot enforce its rights under the rei vindicatio

16. As far as urgency is concerned, there was much debate between the parties as to whether or not Coalcor’s claim for urgency should be upheld.  The respondents pointed out that Islandsite had been in default on its payments under the agreement since February 2017.  Despite this, Coalcor had not sought to take steps to protect its rights in the equipment by cancelling the contract (as it was entitled to do) under clause 13.1.1, and to claim return of the equipment much earlier.  Instead, the respondents contended, Coalcor had waited a year before showing any interest in the current state of its equipment, and only after Islandsite fell into business rescue did it decide to act with urgency.  The respondents submitted that this was a classic instance of self-created urgency: if Coalcor was really concerned about the state of its equipment it should have acted long ago to take steps to protect its position in this regard.

17. Coalcor, on the other hand, submitted that it could not be faulted for failing to take steps earlier to protect its rights in the equipment.  It was not obliged to cancel when Islandsite fell into default initially, and its failure to exercise its rights under clause 13.1.1 could not be held against it.  On the contrary, it had the right to cancel when Islandsite went into business rescue and it had done so.  From the time it elected to cancel, it had acted with the requisite speed to protect its rights by launching the semi-urgent application.

18. In my view, this is not one of those cases where urgency was self-evident. It is common cause that Coalcor had been paid 90% of its contract price.  It had not shown any interest in its equipment for the past year, despite it having every right to protect its position earlier.  There may be merit in the respondents’ submission that this points to a level of complacency on the part of Coalcor at odds with its stated need for urgent protection of its rights in the equipment as professed in the founding affidavit.  However, there is also merit in Coalcor’s submission that it had a self-standing right to cancel and reclaim the equipment when Islandsite went into business rescue.   Be that as it may, the matter was fully canvassed (albeit that both sides were under some pressure to do so) before me and I heard argument on all of the issues.  While it was not ideal to have to deal with these matters on an urgent basis, in my view, it would not be in the interests of justice to non-suit Coalcor on the basis of urgency, and I decline to do so.  In any event, in view of the decision I have reached on the arbitration defence, the question of urgency is somewhat academic.

19. Turning to the issue of the arbitration defence, the respondents submit that under clause 14 of the agreement, any dispute in which final relief is sought between the parties falls to be determined by way of arbitration.  Coalcor seeks final relief following its letter of cancellation and the respondents dispute the validity of this cancellation.  For this reason, and in accordance with the agreement between the parties, the respondents are entitled to enforce the arbitration clause, and to object to the litigation proceeding before the court: the dispute between them must be determined by arbitration.

20. Coalcor opposes the respondents’ reliance on clause 14 of the agreement.  It refers to s6(1) of the Arbitration Act,[1] which provides that:

If any party to an arbitration agreement commences any legal proceedings in any court (including any inferior court) against any other party to the agreement in respect of any matter agreed to be referred to arbitration, any party to such legal proceedings may at any time after entering appearance but before delivering any pleadings or taking any other steps in the proceedings, apply to that court for a stay of such pleadings.” (my emphasis)

21. Coalcor submits that s6(1) is determinative of the procedure to be adopted should a party to litigation intend relying on an arbitration clause as a dilatory defence.  In particular, says Coalcor, the raising of an arbitration defence must be done within the time limits prescribed by this section: i.e. before any pleadings are delivered or any other steps taken.  It points out that the respondents failed to heed these constraints in this matter: they filed an answering affidavit after the institution of the application, they thereafter agreed to the removal of the matter from the roll on the first scheduled hearing date, they filed heads of argument and attended a hearing on 17 May 2018, and they co-operated with Coalcor in requesting a specially allocated enrollment date.  The respondents did not, at any of these stages, seek to rely on clause 14 to insist that the court should not deal with the matter.  It was only after they had taken these further steps in the proceedings that the respondents sought to rely on clause 14 in a supplementary affidavit.  Coalcor submits that, for these reasons, the respondents are precluded under s6(1) from asserting that the court should not adjudicate the dispute.  Alternatively, Coalcor submits that the respondents waived their right to insist that the dispute be adjudicated by an arbitrator, rather than a court.

22. The respondents eschew any reliance on s6 of the Arbitration Act in raising their arbitration defence.  Instead, they state that in raising the defence they sought to exercise their rights under the common law to raise a special plea in abatement.  In the circumstances, the respondents say that they are not bound by the limits prescribed in s6(1): they are entitled under the common law to seek at this stage to enforce the arbitration clause to which both parties held themselves bound.

23. The question of whether the Arbitration Act extinguishes the common law right to rely on an arbitration agreement as a defence to legal proceedings has long been settled in our law.  The short answer is that it does not do so.  As long ago as 1932 the Appellate Division considered this question in The Rhodesian Railways Ltd v Macintosh.[2]  This was prior to the adoption of the present Arbitration Act.  The four provinces (and Southern Rhodesia, in respect of which the Appellante Division had jurisdiction at that time) had separate Arbitration Acts.  The Southern Rhodesian Arbitration Act had a section virtually identical to the present s6(1).  In Rhodesian Railways the question before the court was whether the machinery provided under the Act constituted the only method of staying proceedings pending a determination by arbitration.  The court referred to the earlier case of Walters & Allison[3], with reference to the equivalent s7 of the Natal Act, and the conclusion in that case that:

"the only effect of sec. 7 of the Arbitration Act is that it offers a summary process whereby a person seeking to assert his right may do so immediately after entering appearance in order to avoid the troubles and expense of pleading; but this facility afforded him by the Arbitration Act in no way deprives him of his ordinary right to plead in bar. The terms of the Act are merely permissive."

24. The Appellant Division was invited to reject this view, but instead endorsed it.  The court held in this regard as follows:

It was also argued that the procedure in the Act is inconsistent with the procedure by common law, for if sec. 6(1) of the Act is invoked, the right of going to arbitration is taken away if any steps have been taken in the proceedings, whereas if the submission is invoked in a plea no such consequence follows. I confess that I was at first impressed with this argument, but upon mature consideration it appears to me that there is no substance in it. All that sec. 6 (1) lays down is that you cannot adopt the cheaper and speedier procedure therein provided when once you have delivered pleadings or taken any other step in the proceedings. If you have taken any step in the proceedings, then you can no longer adopt the speedier and less costly procedure of applying to the Court to stay proceedings but you must file your pleadings in the ordinary way. In pleading, however, you can raise the defence that the case ought to be decided by arbitration; this can be done by a special preliminary plea. There is nothing in sec. 6(1) which hints at any intention on the part of the Legislature to alter in any way the common law practice. The section merely provides that a party brought into Court on a contract may at any time after appearance apply to the Court to stay proceedings, and there is nothing in the section that this procedure is in substitution of the former practice. I am therefore of opinion that both the opinion expressed by INNES, C.J., in King v Harris (1909, T.S. 292) and the decision of the Natal Court in Walters v Allison are correct, and that the procedure provided in sec. 6(1) is not obligatory but permissive, and that it in no way derogates from the former practice of pleading the submission clause either by way of a preliminary special plea or by way of a defence. The only difference it may make is with regard to costs.” (my emphasis)

25. The approach adopted in Rhodesian Railways was more recently applied by the Supreme Court of Appeal in PCL Consulting (Pty) Ltd v Tresso Trading 119 (Pty) Ltd[4] where reference was made to the choice a party to an arbitration clause has between relying on section 6(1) of the Arbitration Act, on the one hand, and raising a dilatory plea for a stay, on the other.

26. It follows from this that Coalcor’s starting point in opposing the respondents’ arbitration plea is incorrect: s6(1) is not the sole, and obligatory process in terms of which an arbitration defence may be raised.  Notwithstanding that they had taken further steps, the respondents remained entitled to raise a special arbitration defence on their pleadings, and more specifically, in the affidavits filed by them.  They were not precluded from doing so on the basis of s6(1).

27. I am not persuaded by Coalcor’s alternative submission to the effect that the respondents waived their right to rely on the arbitration defence.  The proceedings were launched by way of urgency.  It is not disputed that the business rescue practitioners have been under considerable litigation pressure over the last period flowing from their appointment as business rescue practitioners in a number of Oakbay entities.  They spell out in their supplementary affidavit the details of the litigation pressure they have faced.  In these circumstances, the raising of the arbitration defence in a supplementary affidavit in urgent proceedings (rather than in their original answering affidavit) before me cannot constitute waiver.

Reference was also made by both parties to an informal approach made by counsel for Coalcor at court before the second scheduled hearing of the matter on 17 May 2018.  It was suggested by counsel, without a formal brief to do so, that the matter might be referred to arbitration.  Respondents’ attorney states that at that time he expressed the prima facie view that the questions raised in the counter-application might be better decided by a court.  He states that due to the urgency of the matter he did not fully appreciate the import of clause 14 of the agreement, which only became apparent to him after he consulted with the respondents’ new counsel before the allocated hearing date.

28. In my view, the attorney’s prima facie response to an informal suggestion of arbitration by Coalcor’s counsel also cannot possibly constitute a waiver of the right under clause 14 to insist that the High Court proceedings should be stayed pending the arbitration of the dispute.  This is particularly so if regard is had to clause 16 of the agreement, which deals with waiver.  It specifically provides that no waiver will be binding for any purpose unless expressed in writing and signed by the party giving it.  Further, no failure or delay of either party in exercising any right, power or privilege will operate as a waiver.

29. Our courts have long upheld the principle that courts should be slow to override the autonomy exercised by parties who agree that their disputes should be settled by way of arbitration rather than by litigation in the courts.[5]  The Constitutional Court in Lefunu Mphaphuli & Associates (Pty) Ltd v Andrews[6] stated this principle as follows:

The decision to refer a dispute to private arbitration is a choice which, as long as it is voluntarily made, should be respected by the courts.  Parties are entitled to determine what matters are to be arbitrated, the identity of the arbitrator, the process to be followed in the arbitration, whether there will be an appeal to an arbitration appeal body and other similar matters.”

30. Coalcor does not dispute the arbitration clause in the agreement.  It accepts that there is a dispute between the parties, and it does not contend that the dispute raised by its letter of cancellation, and the respondents’ counter-application falls outside of the arbitration clause.  Similarly, Coalcor does not contend that there may be exceptional circumstances in this case that would warrant this court taking the extraordinary step of exercising its discretion by refusing to enforce the arbitration clause between the parties.  Our courts have held that because arbitration clauses are based on contractual agreement between the parties, the sanctity of contracts requires that the decision not to enforce an arbitration clause “should only be made where there is a very strong case made out for the parties not to be bound by their agreement.”[7]

31. I am of the view that this is not one of those cases where the parties should be released from their contractual agreement to resort to arbitration, rather than litigation, to settle their dispute.  I note that the parties elected, in clause 14.5 of their agreement to give the arbitrator the power to consider principles of both law and equity when determining matters referred to her or him.  This clause provides that:

The arbitrator need not strictly observe all the principles of law and may decide the matters submitted to him according to what he considers equitable in the circumstances.”

32. In light of this, it seems to me to be appropriate that the dispute arising out of the alleged inequities of Coalcor’s decision to cancel the agreement, and the consequences of this for the parties, should be determined by an arbitrator with these broader powers.  Consequently, there would seem to me to be no special reason why the parties should not be held to their agreement to submit their disputes to arbitration.

33.  For these reasons, I am satisfied that the respondents’ special plea in abatement should be upheld.  Coalcor’s application should be stayed pending the finalisation of arbitration proceedings.  The respondents have consented to arbitration and request that I record their consent in the order.  This finding renders it unnecessary for me to consider the remaining issues in dispute, viz. the s133 issue and the counter-application, the latter issue being part of the dispute for determination by the arbitrator.

34. As far as costs are concerned, I must first determine who should pay the wasted costs of the aborted hearing of 8 May 2018, which were reserved, by agreement between the parties, on that date.  The respondents submitted that the applicant ought never to have proceeded urgently to pursue their relief and for that reason they should be ordered to pay these costs.  I have already indicated that I would not non-suit the applicant on the basis of urgency.  In addition, I note that when it became clear that the matter would be unlikely to proceed on 8 May, the respondents declined the suggestion, made by the applicant on 3 May, that they remove the matter from the Roll at that stage.  In my view, this was unwise of the respondents, who later agreed to the postponement, but only after the wasted costs had been incurred.  For these reasons, they should bear the wasted costs of 8 May 2018.

35. As to the costs of the hearing before me, normally, costs would follow the result.  However, I am mindful that the respondents’ reliance on the common law, and not s6(1) of the Arbitration Act, may have an impact on the issue of costs.  In view of the pressure that both parties were under at the hearing before me, this issue was not canvassed fully at the hearing.  I am minded to reserve the question of the remainder of the costs in order to permit the parties to make further submissions to me in this regard.

36. I make the following order:

1. The application and counter-application are stayed pending the final resolution of the dispute by arbitration in terms of clause 14 of the agreement dated 19 October 2016.

2. It is recorded that the respondents have consented, in terms of section 133 of the Companies Act 2008, to permit the applicant to pursue its claim in arbitration proceedings.

3. The respondents are ordered to pay the wasted costs pertaining to the hearing of 8 May 2018, including the costs of two counsel.

4. The determination of liability for the remainder of the costs is reserved.  The parties may approach my Registrar to make arrangements for further submissions on the question of these costs.

 

 

___________________________________

R M KEIGHTLEY

JUDGE OF THE HIGH COURT OF SOUTH AFRICA, GAUTENG LOCAL DIVISION, JOHANNESBURG

 

DATE OF HEARING        : 24 MAY 2018

DATE OF JUDGMENT    : 14 JUNE 2018


APPEARANCES

APPLICANT’S COUNSEL: B SWART (SC); J MALHERBE

INSTRUCTED BY: STRAUSS ATTORNEYS INC

RESPONDENT’S COUNSEL: LJ MORISON (SC); W BEZUIDENHOUT

INSTRUCTED BY: SMIT SEWGOOLAM INC

 

 

[1] Act 42 of 1965

[2] 1932 AD 359

[3] 1922 NPD 238

[4] 2009 (4) SA 68 at 71H-72C.  See also Street v Dublin 1961 (2) SA 4 (WLD) at 11; Imatu v Northern Pretoria Metropolitan Substructure 1992 (2 ) SA 234 (TPD) at 238 A

[5] See, for example, Telcordia Technologies Inc v Telkom SA Ltd 2007 (3) SCA at 278J-279A

[6] 2009 (4) 529 at 219

[7] Foize Africa v Foize Beheer BV 2013 (3) SA 91 (SCA) at 101F