South Africa: South Gauteng High Court, Johannesburg Support SAFLII

You are here:  SAFLII >> Databases >> South Africa: South Gauteng High Court, Johannesburg >> 2019 >> [2019] ZAGPJHC 175

| Noteup | LawCite

Diesel Power Opencast Mining (Pty) Ltd v Mbali Coal (Pty) Ltd (17/29163) [2019] ZAGPJHC 175 (23 April 2019)

Download original files

PDF format

RTF format


IN THE HIGH COURT OF SOUTH AFRICA

GAUTENG LOCAL DIVISION, JOHANNESBURG

CASE NO: 17/29163

In the matter between:

DIESEL POWER OPENCAST MINING (PTY) LTD                                             Applicant

and

MBALI COAL (PTY) LTD                                                                                         Respondent

 

J U D G M E N T

 

MAIER-FRAWLEY AJ:

 

Introduction

1. Diesel Power Opencast Mining (Pty) Ltd (‘the applicant’) is a mining contractor who was appointed by Mbali Coal (Pty) Ltd (‘the respondent’) to mine minerals (coal) at the Mbali Mine. The mine is located on property[1] over which the respondent (through its holding company) holds mining rights. The respondent is a wholly owned subsidiary of HCI Coal (Pty) Ltd (‘HCI’). HCI was granted a mining right by the Department of Mineral Resources over the property.

2. The provision of mining services was regulated by means of a written ‘Mining of Minerals Agreement,’ which the parties entered into on 19 November 2013 (‘the agreement’). The applicant was appointed to extract coal from the property through an opencast mining operation. It is common cause that the agreement terminated either on 12 or 13 April 2019.[2]

3. On Wednesday the 18th April 2019 the applicant launched an urgent application for spoliatory and ancillary relief. The applicant seeks an order directing the respondent ‘to restore the applicant’s possession’ of :

3.1. the respondent’s coal stockpile on the property;

3.2. the workshop contained on the mine;

3.3. the applicant’s property contained in the workshop and site office on the mine, set out in a list in annexure ‘X’ to the notice of Motion.

4. Further orders sought include ‘authorising the applicant to enclose the coal stockpile at the mine with a fence, or such other practicable means, to prevent unlawful access to the coal stockpile by any third party’ as well as costs of the application.

5. The application was launched on an extremely urgent basis, such that the respondent was afforded less than 24 hours in which to file an answering affidavit before the appointed time for the hearing of the matter at 14h00 on Thursday the 18th April 2019. The application became opposed. The respondent delivered its answering affidavit sometime after the appointed time but before the matter was heard at approximately 3h15 on 18 April 2019.

6. The applicant elected not to file a replying affidavit.[3] As such, the facts and allegations alleged in support of the respondent’s version in the answering affidavit stood undisputed and unrefuted.

7. The matter was opposed on the basis that the applicant had failed to establish its entitlement to relief under the Mandament Van Spolie by reason of the fact that the applicant had failed to establish on its papers that it had been in free and undisturbed possession of the respondent’s coal stockpile. The respondent submitted that not only was no express allegation to that effect to be found in the applicant’s affidavit, no factual basis was either provided in the founding affidavit to ground such a conclusion.

8. It bears mentioning that the respondent denied that the applicant had ever been in free and undisturbed possession of its coal stockpile or that the applicant was unlawfully dispossessed of its equipment and workshop.

9. On the respondent’s version, the applicant did not ever enjoy possession of any stockpile situated on the mine and in any event, the applicant had removed the bulk of its essential working equipment from the mine area by Tuesday the 16th April 2019, i.e., prior to the launch of the application. The applicant had also been afforded access to any remaining equipment[4] left on-site and its workshop prior to the launch of the application.

10. As final relief under the mandament van spolie is sought in these proceedings, the test applicable in the determination of final interdicts finds application. See: Nienaber v Stuckey 1946 AD 1049 at 1053-1054.  The evidence is to be approached on the basis of the Plascon-Evans rule.[5] This means that absent a finding that the averments in the answering papers are so palpably far-fetched or so clearly untenable that they warrant rejection merely on the papers, the matter has to be decided on the common cause facts and on the respondent’s version.[6]

11. The applicant’s founding affidavit was deposed to by Mr Justin Colling (“Colling’), the chief executive officer of the applicant, while the respondent’s answering affidavit was deposed to by Mr Pieter Andries Terblanche (‘Terblanche’), the chief operating officer of HCI.

 

Background Factual Matrix

12. According to the respondent, it does not conduct all aspects of mining activities at the Mbali Coal Mine itself. It procures the performance of some of those functions through third party contractors, such as the applicant, which it did in terms of the parties’ agreement.

13. The mining work which the applicant executed under the agreement involved extracting the coal ore from the ground by removing the overburden and topsoil (i.e., those layers of soil and rocks overlaying the coal seams), carrying out blasting work and removing the coal from its in situ seams, and delivering the raw (‘run-of-mine’, colloquially ‘ROM’) coal to the respondent at a specified ‘Tip area[7] where it is aggregated into a stockpile. The tipping area is in excess of 1,2 kilometres away from the applicant’s working areas at the mine.

14. All mining activities that precede delivery of the coal to the Tip area are carried out by the applicant. After delivery, mining activities, which include the so-called ‘Re-handling’ of the ROM coal, are performed exclusively by the respondent and the applicant has no obligation, right or duty in respect thereof.[8] The physical delivery of the ROM coal to the stockpile at the Tip area constitutes delivery of the product by the applicant to the respondent. It is common cause in these proceedings that the applicant duly delivered the ROM coal to the respondent as required.

15. It was not in dispute that the applicant had established a site office[9] and mechanical workshop at the mine in order to carry out its work, or that it brought all the equipment listed in annexure ‘X’ to the notice of motion onto the mining site. According to the applicant, it employed shift workers that operated its machinery and equipment. The workers are managed by supervisors and managers. Any equipment that was not physically in use was parked and remained on site. This cumulatively ensured that the applicant maintained a presence on site 24 hours per day, 7 days per week.

16. A dispute arose between the parties as to how the agreement terminated[10] and further in respect of the respondent’s communication, on 16 April 2019, of its decision not to make payment to the applicant in respect of its invoices for March 2019 or those yet to be rendered in April 2019.[11] Further disputes relate to a claim for damages which the respondent has asserted apropos the applicant’s alleged non-performance under the agreement.[12]  It is common cause that the disputes arising between the parties under the agreement are to be dealt with at arbitration in accordance with the provisions of clause 19 of the agreement.

17. In a letter addressed by its attorney of record to the applicant’s attorneys of record on Friday the 12th April 2019[13] (dealing with the reasons for the respondent’s cancellation of the agreement on account of a breach by the applicant of its obligations under the agreement, alternatively, the respondent’s acceptance of the applicant’s repudiation of its performance obligations under the agreement), the respondent asserted that it was entitled to employ a third party contractor to carry out the applicant’s obligations on site in order to ensure the proper production of coal from its operations,[14] which it advised the applicant that it intended to do, for which purpose the applicant was instructed to move its equipment to a safe area on the mining premises (which area would be communicated by the respondent to the applicant’s operators on Monday the 15th April 2019).[15]

18. On Saturday the 13th April 2019, the applicant’s attorneys responded to the aforementioned letter advising, inter alia, that the applicant ‘has instructed its staff to cease working immediately and to commence moving its equipment to an area which it considers safe. Our client will commence demobilisation[16] at 07:00 on Monday, 15 April 2019.’

19. According to the deponent to the founding affidavit, the applicant was orally informed on 16 April 2019 of the respondent’s decision not to pay its invoices rendered for work performed in April 2019. In a letter addressed by its attorneys to the respondent’s attorneys on the same day, i.e., Tuesday the 16th April 2019,[17] the applicant laid claim to a right of retention over the respondent’s coal stockpile on account of the value of the coal which it (applicant) had increased by the mining of the coal and threatened inter alia, to seek urgent relief to confirm the professed right of retention.

20. On the same day, being 16 April 2019, the applicant caused 3 trucks to be parked in front of the only 3 entrance gates to the mine, thereby blocking access to and egress from the mine. The blockage prevented any access to the mine for the respondent’s employees and third parties. The respondent states that its plant is located on the mine, and that the respondent employs 90 employees that operate the plant on a daily basis. This action prompted a letter to be sent by the respondent’s attorney to the applicant’s attorney on 17 April 2019 in which the applicant was inter alia, warned that its ‘behaviour’ was unlawful and in criminal breach of South African mining legislation and that the respondent was therefore compelled to remove the trucks in order to restore access to the mining area.

21. According to Colling (deponent to the founding affidavit), he had instructed the applicant’s employees on the mine ‘to exercise the applicant’s common law right of retention and to retain possession of the coal that the applicant had mined and which had been stockpiled at the designated area on the mine’. He states that the ‘only manner in which this could be achieved, given the size of the mine, was to blockade the entrances to the mine.’ He had also instructed the applicant’s employees ‘to retain possession of the applicant’s equipment, workshop and offices on the mine’ due to an (unconfirmed) report which he had received to the effect that the respondent was intent on disturbing the applicant’s possession and causing damage to the applicant’s property, i.e., its equipment, workshop and offices on the mine.

22. According to the respondent, despite requests to the applicant to remove the trucks from the entrance gates, it failed to do so. The respondent avers that it was without its consent and forcibly denied access to its property and it therefore had no choice but to remove one truck from the main entrance.[18] In addition, the blockage of access to and egress from the mine was in contravention of the relevant mining, health and safety legislation. The remaining two trucks were left stagnant in front of the other entrances. [19]

23. On 17 April 2019, the applicant caused a letter of demand[20] to be sent by its attorneys to the respondent’s attorneys in which it recorded, inter alia, the following:

We are instructed that during the course of yesterday evening your client …disturbed our client’s possession of the property over which it is entitled to exercise a right of retention and is refusing our client access to the property of the mine in order to enable our client to restore its possession of the property over which it is entitled to exercise a right of retention.

In addition, your client’s refusal to allow our client access to the property is unlawfully interfering with our client’s rights of ownership of its equipment that is presently situated at the workshop established by our client on the property of the mine, possession of which our client has exercised throughout the duration of the agreement…

The letter concluded with a demand for the restoration of the applicant’s ‘right of retention and possession’ and access to the mine by 12h00, failing which an application to court for urgent relief would be brought. It is clear from what is alleged in paragraph 61 of the founding affidavit that the property, over which the right of retention was asserted in this letter, was the respondent’s coal stockpile.

24. The applicant avers that the respondent’s unilateral action in locking it out of the premises and denuding it of its efforts to preserve its lien is what triggered the launch of this urgent application, warranting the intervention of the court to protect its rights.

25. In oral argument tendered at the hearing of the application, the applicant’s counsel submitted that what is sought by means of these proceedings is the restoration of applicant’s possession (of the coal stockpile and the applicant’s equipment) in confirmation of the applicant’s lien.  Juxtaposed against that case, is the respondent’s version that it ‘alone is and has from inception been in charge and in possession of the stockpile and dealt therewith in its absolute discretion and that the applicant does not, nor did it ever, exercise any control over or had possession of the stockpile.’ The respondent submits that the applicant has failed to prove its possession of the stockpile and has therefore failed to make out a proper case to meet the first requirement of the mandament van spolie.

 

Applicable Legal Principles

Mandament Van Spolie

26. In order to succeed with the mandament van spolie an applicant must allege and prove the following two requirements:

26.1. that he was in peaceful and undistubed possession of the property; and

26.2. that he was deprived of possession unlawfully.

See: Yeko v Qana 1973 (4) SA 735 (AD) at 739 E;

27. In Ngqukumba v Minister of Safety and Security 2014 (5) SA 112 (CC) at paras [10], [12] & [13], the Constitutional Court summarised the applicable principles pertaining to the mandament van spolie as follows:

[10] The essence of the mandament van spolie is the restoration before all else of unlawfully deprived possession to the possessor. It finds expression in the maxim spoliatus ante omnia restituendus est (the despoiled person must be restored to possession before all else). The spoliation order is meant to prevent the taking of possession otherwise than in accordance with the law. Its underlying philosophy is that no one should resort to self-help to obtain or regain possession. The main purpose of the mandament van spolie is to preserve public order by restraining persons from taking the law into their own hands and by inducing them to follow due process.

[12] A spoliation order is available even against government entities for the simple reason that unfortunately excesses by those entities do occur. Those excesses, like acts of self-help by individuals, may lead to breaches of the peace: that is what the spoliation order, which is deeply rooted in the rule of law, seeks to avert. The likely consequences aside, the rule of law must be vindicated. The spoliation order serves exactly that purpose.

[13] All that the despoiled person need prove is that—

(a) she was in possession of the object; and

(b) she was deprived of possession unlawfully.

 

Improvement Lien

28. A lien (right of retention, ius retentionis) is the right to retain possession of another’s property, whether movable or immovable, to secure payment of an amount due to the person retaining possession. It is a means of securing payment of a claim relating to the expenditure of money or something of monetary value by the possessor (termed ‘retentor’ or ‘lien holder’), while exercising his or her lien on that property, until the claim has been satisfied. See: Brooklyn House Furnishers (Pty) Ltd v Knoetze and Sons 1970 (3) SA 264 (AD) at 270. It is apparent that a lien does not entitle the possessor the use of the object: he or she is entitled to hold it as security only.

29. A person who has spent money or done work on another person’s property generally has a right of retention over that property, operating against the entire world. This right may be either a real lien, a salvage and improvement lien, or an enrichment lien. The lien enables the retentor to retain possession of the property in question until the expenditure on the property has been compensated. See: Syfrets Participation Bond Managers Ltd v Estate and Co-operative Wine Distributors (Pty) Ltd 1989 (1) SA 106 (W) at 109H.

30. A lien for the recovery of useful expenses is termed an improvement lien. If successfully raised, the owner may not recover possession of the property from a person who is lawfully in possession and who has an underlying valid enrichment claim, unless and until the defendant has been compensated. See: Singh v Santam Insurance Ltd [1996] ZASCA 92; 1997 (1) SA 291 (SCA).

31. In practical terms, as continued physical possession is a prerequisite for the exercise of a lien, a party exercising the lien will ordinarily not be required to institute legal proceedings to establish and enforce the lien. If such party is wrongfully deprived of possession, its remedy would be to claim a spoliation and pursue a mandament van spolie.[21] Incidentally, one of the requirements for establishing a lien is the possession of the property which is sought to be retained. See: Brooklyn House Furnishers supra.

 

Evaluation

32. It is common cause between the parties that the respondent is the owner of the coal stockpile in question and that the applicant duly delivered the raw coal in question to the respondent. On the undisputed evidence of the respondent, the applicant mined the coal and then immediately delivered the coal to the respondent where after it enoyed no further control or possession of the coal. Delivery was effected at the Tip area by aggregating the coal into a stockpile. The respondent is and was at all times in sole, permanent control of the Tipping area, the stockpile and the plant (where Re-handling occurs). Once delivery takes place, the respondent acquires exclusive possession and control of the coal that has been stockpiled.  Moreover, the undisputed evidence of the respondent is that the stockpile consists of a mere 1500 tonnes of unprocessed coal with a market value ‘as is’ of approximately R275 000.00.

33. Salient aspects of the factual averments made in support of the respondent’s version are quoted below for ease of reference:

[14] The physical delivery of the ROM coal to the stockpile at the Tip area, constitutes delivery of the product by Diesel Power to the respondent.

 [15] Forthwith upon the ROM coal so being delivered, the respondent takes possession and control of that material for so-called ‘Re-handling’. Re-handling entails crushing the ROM coal to the size stipulated by the end-buyer and thereafter washing (and blending, if necessary) the coal to achieve the required chemical, mostly calorific profile stipulated by [the] end-buyer.

 [16] This re-handling is performed exclusively by the respondent. Diesel Power has no obligation, right or duty in respect thereof. It has no involvement with or right to the ROM coal once it is delivered to the stockpile at the Tip area.

 [17] …when the agreement was negotiated, all the parties envisaged that, at any given moment, a sizeable stockpile would exist. Indeed, if diesel Power were to have complied with its production obligations, such would have been the case. However, given its persistent production shortfalls, no stockpile of any meaningful reserves was ever accumulated. Simply put, whatever ROM coal was delivered by Diesel Power was taken up and processed as soon as possible by the respondent, in order to minimise, as far as possible, its own delivery shortfalls to the end-buyers.

 [18] …the respondent, at all times without exception, received delivery of the ROM material as it was placed on the (mini) stockpile at the Tip area, hence it “Re-handled’ the material, to the complete exclusion of Diesel Power.

 [19] The Tipping area is on average in excess of 1,2 kilometres away from the Diesel Power working areas. Diesel Power has, and had, no presence of any kind at the Tipping area. Its sole activity at the Tipping area was that its vehicles arrived for the sole purpose of tipping the ROM coal onto the stockpile and then immediately to return to the Diesel Power working area.

 [20] The respondent is, and was at all times, in sole, permanent control of the Tipping area, the stockpile and the plant (where Re-handling) occurs.

 [21] The respondent does not and did not report to or seek any permission from Diesel Power to deal with the stockpile. In short, the respondent alone is and has from inception been in charge and in possession of the stockpile and dealt therewith in its absolute discretion. Diesel Power does not, nor did it ever, exercise any control over or ha[ve] possession of the stockpile.  ”

34. The applicant elected not to engage with the substantive allegations made by the respondent in the answering affidavit. The allegations in the answering affidavit (quoted above) may therefore be taken as established facts.[22]

35. The founding affidavit contains a glaring absence of any description or evidence concerning the stockpile located on the mine or of any control and possession as may have factually been exercised by the applicant in relation thereto. Save for a few bald assertions as to the applicant’s possession in the correspondence of the applicant’s attorneys (for which no factual basis is provided) and one single allegation made without substantiating particularity in para 21 of the founding affidavit, to wit, that the respondent ‘…had thus unlawfully disturbed the applicant’s possession of the stockpile’, no-where is it alleged that the applicant was in free and undisturbed possession of the stockpile, supported by factual evidence to ground such conclusion.  Even assuming in favour of the applicant, namely, that the issue of its possession was sufficiently pleaded in the founding affidavit[23] (a matter of which I am not convinced),[24] the respondent made factual allegations that effectively belied such allegation in the answering affidavit. Insofar as the respondent’s allegations thereby raised a real dispute of fact on the papers (and I cannot find otherwise), by virtue of an application of the Plascon-Evans rule, the applicant would not be entitled to relief upon a consideration of the common cause facts[25] and the respondent’s version, which cannot be rejected out of hand.

36. During oral argument presented in court, the applicant’s counsel submitted that by virtue of the provisions in the agreement, in particular, the definition of ‘the property’[26] (at p. 60 of the papers) as read with clauses 2.4 and 3.1 of the agreement,[27] if the applicant was entitled to possession of the greater (i.e., the whole property - the whole mine), why would it not be entitled to possession of the lesser (i.e., the coal stockpile located on the property)? The argument, however, loses sight of the respondent’s undisputed evidence pointing to the facto position which is that it alone had and retained possession of the coal stockpile pursuant to delivery of the ROM coal. The applicant has therefore failed to prove that it was in free and undisturbed possession of the stockpile, notwithstanding its perceived entitlement to possession under the agreement.

37. During oral argument, the applicant’s counsel relied on the unreported decision of Close-up Mining (Pty) Ltd v Canyon Resources (Pty) Ltd (77941/2014) [2014] ZAGPPHC 981 (13 November 2014), a judgment of Bertelsmann J in the Gauteng Division,[28] For ease of reference, this case is referred to hereinafter as ‘the Bertelsmann judgment.’.[29] There Bertelsmann J stated that the work conducted upon the mining site by the mining contractor was by its very nature such that the mining operator had exclusive possession of the mining site (and shared possession of the yard) in order to fulfil its statutory functions and to carry out the work it contracted to perform, namely, the removal of coal from the opencast mine. The facts in that case demonstrated that the contractor was the primary user of the Yard, that its machines to the value of millions were stored there and that it had never relinquished possession thereof.

38. It should be noted that the conclusion reached by the learned judge in the Bertelsmann judgment (in relation to the contractor’s possession of the mining site and Yard) was supported on the peculiar facts of that matter. I agree with the respondent’s counsel that the Bertelsmann judgment is distinguishable on the facts of the present matter and as such, is not binding upon me. [30] Firstly, in the present matter the applicant is not seeking to exercise or preserve a retention right over the entire mine, as was the case in the Bertelsmann judgment. Secondly, the facts in the Bertelsmann judgment supported the conclusion that the applicant had possession of the mining are. Thirdly, the issue of the possession and control of the tipping area or any coal stockpile thereat did not arise for consideration, as is the case in the present matter.

39. The question of whether or not a party is in free and undisturbed possession of property such as to entitle it to relief ounder the mandament van spolie is required to be proven by means of evidence presented in its affidavits. At the risk of sounding repetitive, in the present matter, no substantiating factual evidence was presented by the applicant in support of its professed ‘possession’ of the respondent’s coal stockpile or in refutation of the respondent’s version that it (respondent) was in sole and exclusive possession thereof at all times. Moreover, on the respondent’s version, the stockpile has a minimal monetary value and even if the stockpile were to be have been held capable of being subject to a lien, it would not have served the purpose of securing payment to the applicant of its unpaid invoices, which aggregate in total an amount in excess of R16 million.

40. Given that (i) the applicant had already commenced demobilisation operations of its equipment two or three days before it sought to assert a lien over the coal stockpile (which property, on a consideration of the respondent’s undisputed version and other common cause facts, cannot be found in these proceedings to have been in the applicant’s free and undisturbed possession, whether at the time that the lien was sought to be asserted or when the respondent removed the applicant’s truck from the main entrance to the mine or at any other time prior thereto; and (ii) that the applicant had, on the respondent’s version, already removed most of its equipment from the mine by Tuesday the 16th April 2019 and had been afforded access to the balance of the equipment that remained behind, it is axiomatic that the second requirement for relief under the mandament van spolie  has not been met.  The relief sought in paragraph 3 of the notice of motion accordingly cannot be granted.

41. It follows from the aforegoing that the application falls to be dismissed.

42. Mr Badenhorst SC who appeared for the respondent, submitted that the application was ill-conceived and brought in respect of a coal stockpile having a value that is so unsubstantial as to justify the invocation of the maxim ‘de minimis non curat lex.[31] Moreover, the application was launched as a matter of extreme urgency, the day before the public holiday that heralded the start of the Easter long weekend, in circumstances where the respondent was afforded less than 24 hours in which to note its opposition and to file its answering affidavit and where the application was based on a lack of factual evidence or evidence that was insufficient for making out a proper case in order to meet the essential elements or requirements of the mandament van spolie. By virtue of the inordinately curtailed time constraints imposed upon it, the respondent was subjected to extreme inconvenience and hardship and moreover had to suffer the attendant expense of having to defend an unsustainable or unmeritorious claim. All these circumstances, so it was submitted, warrant the imposition of a punitive costs order.

43. Mr. Vetten who appeared for the applicant, persisted in seeking relief in terms of the notice of motion, together with costs.

44. Although the allegations in the founding affidavit were advanced without a proper factual basis, as indicated above (at least as regards the issue of its possession of the respondent’s stockpile), the litigation appears to have been pursued in the genuine albeit mistaken belief that a factual[32] and legal basis[33] existed for the relief sought therein. The fact that the stockpile itself holds nominal value,[34] all things considered, is not of its own definitive of the debate. The application was indeed brought as a matter of extreme urgency. I cannot however conclude that this in itself, together with the severely curtailed time constraints imposed for the filing of papers, amounted to an abuse of the process in the light of the respondent’s election, at the hearing of the matter, not to persist with its opposition in regard to urgency and did in fact file a succinct yet sufficiently detailed affidavit in opposition to the matter within the time available.

45. For these reasons, I am inclined to exercise my discretion in awarding costs on the ordinary scale in keeping with the general rule pertaining to costs.

46. I accordingly make the following order:

 

ORDER:

1. The application is dismissed.

2. The applicant is to pay the costs of the application on the scale as between party and party.

 

 

_________________

MAIER-FRAWLEY AJ

 

Date of hearing:                                  18 April 2019

Judgment delivered                            23 April 2019

 

APPEARANCES:

Counsel for Applicant:                        Adv. D. Vetten

Attorneys for Applicant:                     Edward S Classen & Kaka

                                                            Ref: E. S. Classen

Counsel for Respondent:                     Adv. C. Badenhorst SC

Attorneys for Respondent:                  Mervyn Taback Incorporated

                                                            Ref: L. Van Staden

 

[1] The property  in respect of which a mining right was granted to the respondent and in respect of which the respondent appointed the applicant to perform mining or mining services, includes portions 16, 17, 20, 31 and the remaining extent of portion 9 of the Farm Klippoortjie 32 I.S, measuring 204,779 hectares, on which the Mbali Coal Mine is located.

[2] The applicant avers that the agreement terminated on 13 April 2019. The respondent points out that it terminated on either 12 or 13 April 2019. The respondent’s letter of 12 April 2019 (referred to in para 16 of the judgment below) suggests that the agreement was cancelled by the respondent on 12 April 2019.

[3] Notwithstanding delivery of a succinct yet relatively detailed answering affidavit, the Applicant forged ahead in its quest to obtain relief on the papers filed, in spit of the emergence of a material dispute arising between the parties on the question of whether or not the applicant had been in free and undisturbed possession of the respondent’s coal stockpile (before the alleged dispossession thereof), such as to entitle it to relief under the Mandament Van Spolie.

[4] The only equipment in working condition that remained on site, were three excavators. Apart therefrom, the balance of the remaining equipment on site by this date comprised unworkable equipment that was ‘broken, scrap or in need of repairs.’ The respondent had addressed a letter to the applicant on Wednesday the 17th April 2019 providing it with access to remove the remainder of the equipment contained at the workshop, thus obviating the need for an urgent application.

[5] The approach – to factual disputes in motion proceedings for final relief – has been formulated in in Plascon-Evans Paints Ltd v Van Riebeeck Paints (Pty) Ltd [1984] ZASCA 51; 1984 (3) SA 623 (A) at 634H-635C. In its simplest form, this approach means that the application will be determined on the version stated by the respondent in the answering affidavit, unless the allegations in the answering affidavit are capable of being rejected out of hand.

[6] The Plascon-Evans principle was restated and expounded in National Director of Public Prosecutions v Zuma [2009] ZASCA 1; 2009 (2) SA 277 (SCA) at para [26]. See too: Wightman t/a  JW Construction v Headfour (Pty) Ltd and Another [2008] ZASCA 6; 2008 (3) SA 371 (SCA) at paras [12]-[13].

[7] The Tip area is defined in the Scope of Works, annexure ‘B” to the agreement, a copy of which appears at pp.144-151 of the papers. Clause 5f of the Scope of Works expressly provides that the applicant will mine ‘and deliver the coal to the plant tip’.

[8] See paras 15 of the answering affidavit (at p. 130 of the papers) where the respondent states as follows: ‘This re-handling is performed exclusively by the respondent. Diesel Power [applicant] has no obligation, right or duty in respect thereof. It has no involvement with or right to the ROM coal once it is delivered to the stockpile at the Tip area.’‘

[9] The site office is the property of the applicant and consists of a converted container office containing movable property such as furniture and computer equipment, stationary, records and the like.

[10] The dispute is about whether or not the applicant has complied with its obligations under the agreement and the lawfulness of the respective parties’ conduct in respect of the cancellation of the agreement.

[11] The applicant avers that invoices to the value of R16,437,952.40 were rendered by the applicant to the respondent on 9 April 2019 and that there is no dispute that services to that value were rendered and that the amounts of the invoices are presently due and owing and payable. (see para s 28-29 of the founding affidavit).

The respondent submits that itis entitled to withhold payment of any amounts due in terms of the monthly invoices until such time as its claims against the applicant in respect of the applicant’s rehabilitation obligations have been determined, given the admitted perilous financial condition of the applicant. The value of the rehabilitation liability will only be determined after the applicant vacates the site. The respondent avers that the applicant is indebted to it in ‘very substantial amounts’, the particulars of which still have to be quantified, which liability arises from the applicant’s repeated admitted and continuous failure to comply with its target performance obligations under the agreement. The respondent states that if it were to pay the amounts of the invoices, the proceeds would likely immediately be dissipated to pay the applicant’s creditors, leaving it with no funds to settle its rehabilitation obligations and the damages liability (for the shortfall in production) owing to the respondent, given that the applicant, on its own version, lacks the financial resources to meet its own financial obligations (see paras 33-34 of the founding affidavit) and given that the amounts it demands now be paid, are required by it to stave off liquidation (see para 49 of the founding affidavit). In those circumstances, the respondent submits that it is entitled not to make payment of any amount to the applicant arising from the mining agreement until the applicant shall simultaneously pay the amounts due by it arising from the same agreement (see paras 26-32 of the answering affidavit).

[12] Curiously, the letter dated 14 March 2019, a copy of which appears at pp.161-163 of the papers, evidences, to some extent, the applicant’s admitted non-performance.

[13] A copy of this letter appears at pp.31-33 of the papers.

[14] See paras 38- 42 at pp. 135-136 of the papers.

[15] See p. 33 of the papers.

[16] The ordinary meaning of ‘demobilisation’, as understood and applied within the context of the present matter, is to stop all operations and to release or discharge or disband applicant’s employees on the mine. (See: https://www.dictionary.com/browse/demobilization; and https://dictionary.cambridge.org/dictionary/english/demobilize).

[17] No proof of transmission was provided by the applicant in its papers to indicate the time at which this letter was electronically dispatched.

[18] According to the respondent, the truck was safely moved to the side of the road. This appears to have taken place later in the evening on 16 April 2019.

[19] The applicant avers in para 61 of the founding affidavit that as from Tuesday night on 16 April 2019, the respondent ‘has locked the applicant out of the premises, by closing off the road that gives access to its mine office and workshops; they have posted security guards and a police van to prevent entry upon the property. The result is that the applicant cannot get near its property, or exercise a lien over the stock pile of coal. The coal trucks do have access and are removing the coal from the mine.’

Interestingly, the respondent makes the point in the answering affidavit that the ‘mere fact that Diesel Power [applicant] reverted to hostile attempts on 17 April 2019, and on its own admission that it could only do so [by] blocking the entrance to the mine, ostensibly to take possession of the stockpile illustrates that it never had possession of the stockpile to start with. It came as an afterthought to Diesel Power and was nothing but extortion.’

[20] The time at which the letter was electronically dispatched does not appear from the papers but it appears from the context that it was sent before the respondent’s letter in reply (referred to in para 20 of the judgment)..

[21] See: Peter Van Blerk, ‘Precedents for applications in Civil Proceedings’, para [46.4] at p.497.

[22] See: Boxer Superstores Mthatha and another v Mbenya 2007 (5) SA 450 (SCA) at para 4. Albeit that Cameron JA’s remarks were said in a different context, the principle set out therein remains relevant and apposite.

[23] It must be remembered that in application proceedings, the affidavits do not only constitute evidence, but they also fulfil the purpose of pleadings. The affidavits must therefore set out the cause of action in clear and unequivocal terms to enable the respondent to know what case to meet. See: Molusi and others v Voges No and Others [2015] 3 All SA 131 (SCA) at para [20].

[24] The applicant’s case for its professed possession of the stockpile is contained in paras 53-61 (at pp.27-28) of the founding affidavit. Not a single averment is made therein to either allege that it was ever in free and undisturbed possession of the respondent’s stockpile, nor are facts set out to justify such a conclusion being drawn. Whilst allegations are made in regard to its equipment and site office, which it is common cause, are owned by the applicant and which were in its possession before the retaliatory action of the respondent, the substantiating evidence tendered by the respondent indelibly points to the conclusion that the applicant was afforded access to its workshop and equipment prior to the launch of the application, and in fact, on its own say-so, commenced removal of the equipment and demobilisation operations as early as Saturday the 13th of April 2019, some 4 days before the launch of the application.

[25] The common cause facts (or facts left undisputed are set out in paras 11-22 & 33 of the judgment.

[26] See fn 1 above where the property is defined.

[27] In terms of clause 2.4, notwithstanding the termination of the agreement, the applicant is responsible for properly rehabilitating the property, excluding the Excluded areas (as defined). The argument raised in this regard is that the applicant has to be in possession of the property in order to fulfil its rehabilitation obligations. The argument loses sight of the fact that once the coal is delivered, the respondent may do with it as it pleases. In any event, no evidence was tendered by the applicant in respect of its rehabilitation obligations or that such obligations extend to the possession by it of the respondent’s coal stockpile., 

In terms of clause 3.1 of the agreement, the applicant was appointed to perform mining on the property for the duration of the agreement, but subject to the overall control of the respondent.

[28] As appears from the Bertelsmann judgment, the learned judge cautioned that it had to be read with the judgment under Case No. 69101/2014 between the same parties and Zonnebloem Coal (Pty) Ltd (in the matter of Canyon Resources (Pty Ltd & Zonnebloem Coal (Pty) Ltd v Close-Up Mining (Pty) Ltd [‘the Zonnebloem judgment’]).

In the Zonnebloem judgment, the holder/s of the mining right [Close-Up and/or Zonnebloem – the ‘other parties’] had brought an urgent application against the mining contractor [Canyon] for possession of the mining site (being the property on which the contractor had performed the mining operations) pursuant to the contractor having exercised a retention lien over the mining site. The contractor brought a counter-application, seeking restoration of its possession of the mining site after its employees were ‘forcibly encouraged’ by the representatives of the other parties to leave the site. The counter-application was for spoliatory relief, whilst the main application concerned the right to the lien that had been asserted by the contractor (which was in dispute) and the other parties’ right to possession of the mining area upon the furnishing of security for the payment of the contractor’s outstanding invoices. A dispute had arisen between the parties in relation to the non-payment of the contractor’s invoices, which resulted in the relationship between the parties terminating. The contractor claimed that it was still owed a considerable sum (in excess of R17 million) whilst the other parties claimed that it (the contractor) had been over-paid pursuant to the contractor’s over-invoicing. The contractor immediately asserted a lien over the mining area until it was paid, whilst the other parties demanded its immediate vacation of the mining area. The other parties disputed the contractor’s right to a lien, asserting that the contractor was never in possession of the mining area as it had entered the site under the alleged control of the other parties. The court found that the probabilities favoured the contractor’s version as to its possession of the mining site, holding that possession sufficient to establish a lien had been established on the specific facts of the matter. It was not in dispute that the contractor had brought heavy machinery worth R100 million on-site to execute its contract, which machines had remained on-site even when the other parties had ‘forcibly encouraged’ the contractor’s employees to vacate the site and had thereby spoliated the contractor of its possession of the site. Bertelsmann J found that the contractor had been in possession of the mining site, inter alia, because the facts showed that the other parties (mining right holder/s) had not had any business to conduct on the mining area while mining was being conducted thereat by the contractor, and also did not have a presence of any employee there on a permanent basis (which facts are distinguishable from the facts of the present matter in that the respondent did maintain a presence of employees at the Mbali mine and did, on its undisputed version, in fact conduct business thereat). The court found that the occasional access that the other parties may have exercised to the mining site was for a limited purpose and certainly not to assert possession (contrary to the facts of the present matter where the respondent did in fact assert its sole possession of the stockpile at the Tip area). Relying on authorities of higher courts, Bertelsmann found that while the mining operator could not perform its work without the holder of the mining right allowing it to enter the operational area, such permission was not in conflict with the contractor’s intention to take possession until its contract has been fulfilled and its remuneration has been paid.

[29] In the Bertelsmann judgment, the mining contractor [Close-Up] had brought an urgent application for an interdict to prevent the respondent from interfering with its lien, pending the final resolution of the parties’ dispute by arbitration. A dispute arose in regard to payment of the amounts invoiced by the contractor [applicant] for coal it had mined and delivered to the respondent. The respondent refused to pay the invoices, contending that it had overpaid the applicant by some R50 million and that the applicant’s claim had been erased by set-off. The agreement was cancelled pursuant to the applicant’s acceptance of the respondent’s alleged repudiation of the mining contractor’s agreement. Upon cancellation, the applicant immediately laid claim to a lien over the mining area and the Yard, until all its claims had been satisfied. The respondent through its employees attempted to enter the mining area, which the applicant had blockaded with a protective ring of security guards, to prevent access to the mining area and Yard. The respondent launched a counter-application for restoration of the possession of the mining area, claiming to have been in control thereof. It was not in dispute that the respondent conducted operations such as washing of coal, stockpiling of coal and performed administrative and management functions on premises surrounding the mining area i.e., at premises, next to and around the mining area. The respondent had access to the car park and to all other ‘installations and equipment’ situated around and near to the mining area. Yet it nonetheless wanted access to the mining site, which Bertelsmann found, on the peculiar facts, were in the applicant’s exclusive possession and therefore capable of establishing a lien. The applicant maintained that it was the primary user of the yard, that its machines to the value of millions of rand were stored there and that it never relinquished possession thereof. The judgment also dealt with the question of whether or not the applicant had a claim that justified the recognition of a lien. Expert evidence as was tendered to show that the applicant’s invoices reflected a distorted picture of the actual coal mined and that the respondent had been overcharged by some R50 million.  Respondent relied on these reports to assert that set-off operates and that it is not indebted to the applicant at all. The applicant disputed the expert reports. Bertelsmann J found that the disputes could not be resolved in the interdict proceedings and that the applicant’s liquid claims were not extinguished by set-off as the respondent’s claims were clearly illiquid. Further, the applicant was ‘clearly in possession of the mining area and the Yard’ as the work conducted upon the mining area by the applicant ‘is by the very nature thereof such that the mining operator must have exclusive possession thereof in order to fulfil its statutorily determined functions and to carry out the work it contracted to perform, namely the removal of coal from the opencast mine.’

[30] The Bertelsmann judgment was concerned with possession of the entire mining area and yard, being the property forming the subject matter of a lien which the applicant sought to preserve. The outcome arrived at was fact-dependent and fact-intensive, meaning that the learned judge’s conclusion that the applicant in that matter enjoyed exclusive possession of the mining area was arrived at upon a consideration of all the facts, including the fact that the respondent conducted all of its activities or operations on premises surrounding the mining area and not upon the mining area. In the present matter, the facts put up by the respondent (in contrast to the lack of facts put up by the applicant in regard to the tipping area) showed that the applicant has and had no presence of any kind at the tipping area, whether before and after delivery of the coal to the respondent.  The applicant’s counsel argued that the present matter concerns the confirmation of a lien (as opposed to the preservation of a lien as in the Hartzenberg judgment), however, the issue of whether or not the applicant had even established a lien, although not something I was required to determine in the present matter, was in any event predicated on its possession of the stockpile, which was not established by it in these proceedings. (Underlining own emphasis)

[31]De minimus’ is a Latin expression meaning ‘about minimal things,’ normally in the locutions ‘De minimus non curat lex’. It has sometimes been said to be a common law principle whereby judges will not sit in judgment of extremely minor transgressions of the law. It has been sometimes been restated as: the law does not concern itself with trifles.

[32] By virtue of the provisions of the agreement that afforded the contractor possession of the mining area on which to conduct the mining or mining services.

[33] By virtue of the Bertelsmann judgment - where the learned judge concluded that the contractor had exclusive possession of the mining area by virtue of the nature of the work conducted by it on the mining area.

[34] No evidence having been put up by the applicant as to the value of the coal stockpile.