South Africa: Supreme Court of Appeal

You are here:
SAFLII >>
Databases >>
South Africa: Supreme Court of Appeal >>
1999 >>
[1999] ZASCA 82
| Noteup
| LawCite
A A Alloy Foundry (Pty) Ltd v Titaco Projects (Pty) Ltd (309/97) [1999] ZASCA 82 (12 November 1999)
Download original files |
OF SOUTH AFRICA
Case No. 309/97
In the matter
between:
A A ALLOY FOUNDRY (PTY) LIMITED
Appellant
and
TITACO
PROJECTS (PTY) LIMITED Respondent
Court: GROSSKOPF, HARMS, ZULMAN JJA, and MELUNSKY and MPATI AJJA
Heard: 2
NOVEMBER 1999
Delivered: 12 NOVEMBER 1999
Damages
due to breach of contract - loss of management time - collateral benefits.
Attorney and client costs.
JUDGMENT
HARMS JA:
[1] The plaintiff (the present respondent) was employed during
1989 by Purity Ferrochrome (Pty) Ltd (hereinafter referred to as "Purity")
to
design, supply, erect and commission a smelter for smelting chromate ore at
Purity's ferrochrome plant in Rustenburg. This included
the provision of two
furnaces. A Japanese concern, Tanabe, as subcontractor, supplied the necessary
technology and commissioning
and engineering services. Each furnace has three
electrode columns, the extremities of which penetrate the ore mix and generate
the heat necessary for smelting. Electric current is transferred through
contact shoes to the upper part of the electrodes, each
being serviced by eight
shoes in such a way that the shoes are not directly in contact with the ore mix.
Contact shoes have more
the appearance of shoe soles than of shoes, are concave
on the inner surface in order to fit snugly around the electrodes and have
cavities for circulating cooling water.
[2] They are conventionally made of
either brass or copper, each shoe weighs several hundred kilograms and is about
1,25m in length
and 0,5m wide. A casting process is used to manufacture them
and the defendant (the appellant), who operates a foundry, was subcontracted
by
the plaintiff to produce 48 shoes made of brass. In due course the defendant
provided the shoes ordered; they were installed
and soon gave problems. The
plaintiff, Purity and the project manager had great difficulty in establishing
the cause of the problems
and eventually came to the conclusion that it was
because the defendant had used a brass alloy which did not conform to the
British
Standards Specification (BS 2870/1980 CZ103). In the event, the
plaintiff rejected the shoes, tendered redelivery and claimed damages.
An
alternative claim based upon an alleged repudiated settlement and which was the
subject of separate adjudication was
dismissed.[1] The damages claim
succeeded before Heher J and this appeal is with his leave.
[3] Brass is an
alloy of copper and zinc and, depending on its intended application, the ratio
between them may vary. Impurities
are always present and the nature and quality
of the brass depend upon the identity of any particular impurity and the amount
present.
The said specification prescribes an 80:20 copper-zinc alloy with a
maximum lead content of 0,05% by mass. It became common cause
that the brass
used by the defendant contained lead far in excess of the prescribed maximum.
Generally speaking, lead deleteriously
affects the quality of brass and the
higher the lead content the greater the loss of ductility and this, depending
upon the operating
conditions, may manifest itself in cracking. The scientific
explanation is fairly simple. Lead does not dissolve in brass like
sugar does
in water but remains undissolved, much like sand. Due to its low melting point
of 327° C, it will start melting
long before the alloy which melts at
about 1000° C. Once the lead melts it weakens the brass.
[4] The first
issue to decide is whether the defendant was contractually obliged to supply
brass shoes with less than 0,05% of lead
by weight in accordance with the said
British Standard. The answer to the question depends upon the interpretation of
clause 1 of
the written contract (the "purchase order") between the parties.
Clause 1 provides that:
"This purchase order ... constitutes the sole and entire agreement between the parties hereto. The Contractor's quotation is incorporated in and made a part of this purchase order only to the extent of specifying the nature and description of the goods ordered. ... No other terms or conditions shall be binding upon Purchaser unless accepted in writing."
The focus
is on the identification of the defendant's "quotation": the plaintiff's case is
that the quality control plan prepared
by the defendant which specified that the
material to be used for the contact shoes would conform to the British Standard
was part
of the quotation and was incorporated into the purchase order because
it specified the nature and description of the goods ordered.
Although
admitting the existence of the plan the defendant denies that it formed part of
its "quotation".
[5] Heher J held that if it were established that the
defendant had submitted the plan as part of its quotation, compliance with
the
plan would have been a contractual obligation. He found that a document
entitled "Quotation", together with the plan, was submitted
to the plaintiff by
the defendant in one envelope, and that before the conclusion of the contract
these two documents were discussed
and considered together by both parties.
These findings, which are relevant in identifying the "Contractor's quotation"
referred
to in clause 1 of the purchase order, were rightly not attacked on
appeal. Corroboration for this finding is to be found in the
fact that there
was a reason why the defendant would have provided a quality plan as part and
parcel of its quotation. According
to the tender documents provided to the
defendant and on which the tender had to be based, the defendant was obliged to
"submit with
his tender details of his quality plans". In particular, the
defendant was called upon to submit "full details of the brass selected"
for the
contact shoes and the said British Standard was suggested. The document headed
"Quotation" itself did make reference to
the nature of the brass by stating that
the copper-zinc ratio would be 80:20 - which was in any event the prescribed
according to
the drawings prepared by Tanabe and provided to the defendant - but
it did not provide the required full details of the brass selected.
That was
set out in the accompanying plan. These facts satisfy me that Heher J was
correct in concluding that the quotation referred
to in the purchase order was
intended by the parties to include the quality plan. Evidence of such an
identifying nature is permissible
and does not infringe the parol evidence rule
(Van Wyk v Rottcher's Saw Mills (Pty) Ltd 1948 (1) SA 983 (A) esp at
990-992).
[6] Having used brass which does not conform to the prescribed
specification, the question that arises is whether the defendant was
in breach
of clause 12 of the purchase order which reads:
"Contractor warrants that the goods shall be free from defects in ... material ... and shall conform in all respects to the terms of the purchase order. ... If it appears within one year from the date of placing the equipment into service for the purpose for which it was purchased, that the equipment or any part thereof, does not conform to these warranties, and Purchaser so notifies Contractor within a reasonable time after its discovery, Contractor shall thereupon promptly correct such nonconformity at its own expense. ... Except as otherwise provided in this purchase order, Contractor's liability shall extend to all damages proximately caused by breach of any of the aforegoing warranties or guarantees, but liability shall in no event include loss of profit or loss of use ..."
To the extent relevant to this case, the clause
contains two separate and distinct warranties: the goods were to be free from
defects
and, second, the goods had to conform in all respects to the terms of
the purchase order. In the light of the foregoing, it follows
that the brass
supplied was not in conformity with the terms of the order. Because the general
principle is that contracts must
be in forma specifica rather than
by way of equivalents (cf Maennel v Garage Continental Ltd 1910 AD
137 at 148; Algoa Milling Co Ltd v Arkell and Douglas 1918 AD 145 at
158; Tulbagh Municipality v Waveren Building Contractors (Pty) Ltd and
Others 1966 (4) SA 618 (A)), the defendant's failure amounted to a breach of
contract.
[7] Since the defendant refused to rectify the breach in terms of
the quoted clause, the extent of its liability has to be determined.
The
plaintiff rejected the shoes and offered to return them to the defendant. As a
result, the plaintiff had to replace them and
supply Purity with another set in
terms of its main obligation under the construction contract which was to supply
contact shoes
for the smelter in accordance with its design. It then again
matters not whether the shoes failed because of excessive quantities
of
lead.
[8] Purity, in the meantime, had sold its smelting business,
comprising all its assets as a going concern to Consolidated Metallurgical
Industries Ltd ("CMI") and at the time when the shoes were rejected, Purity had
no further interest in their replacement. The plaintiff
negotiated the
replacement of the 48 shoes with the new owner of the smelter. It settled by
undertaking to provide CMI with 16 copper
shoes which costs R183 325 together
with a payment of R200 634, an alternative which was much cheaper than supplying
CMI with 48
new brass shoes of acceptable quality. The case was argued on the
assumption that liability of the defendant for the payment of
these sums
depended on whether Purity's rights to performance in terms of the construction
contract had devolved upon CMI, the supposition
being that in the absence of a
contractual obligation towards CMI, the plaintiff could not have suffered any
damages. I shall assume
that this approach is correct. Although CMI purchased
all Purity's assets - and its rights against the plaintiff would obviously
fall
within that category - the fact of the matter is that the sale agreement, whilst
providing a list of ceded contracts, omitted
a reference to the construction
contract. Nevertheless it did provide for a cession of the plaintiff's
performance guarantees.
At the time it was not suspected that the defendant had
failed to supply shoes conforming to the British Standard; to the contrary,
the
defendant, innocently it seems, had transmitted to the plaintiff analysis
certificates which certified due compliance.
[9] Finding in favour of the
plaintiff, Heher J relied heavily upon a warranty clause in the CMI contract. I
have some hesitation
in accepting the correctness of his interpretation and
prefer to base my judgment on another ground. Since Purity had sold all the
assets of the going concern to CMI, any contingent rights against the plaintiff
- in this case a claim for the supply or resupply
of the shoes - were part of
the object sold. As a witness attempted to point out, it hardly made sense for
CMI to have taken cession
of the performance guarantees if the right to enforce
the primary performance did not also vest in CMI. The same witness, Smidt,
who
was recalled after the point had arisen for the first time during argument,
testified that as far as he could recollect, the
plaintiff had signed a cession
(he probably meant a consent to a cession) to CMI with respect to discharging
all of its obligations
in terms of its relationship with Purity. Although he did
not produce the document, his evidence was not challenged and accords with
the
probabilities having regard to the conduct of the parties involved after the
sale. Even the defendant took part in the negotiations
with CMI on the
replacement of the contact shoes.
[10] Two heads of damages were debated
before us. The first concerns the damages suffered as a result of the plaintiff
having settled
with CMI, a matter alluded to in par [8] above. In summary, the
plaintiff settled with CMI, undertaking to provide 16 copper shoes,
making a
cash payment and providing a performance guarantee in respect of the new shoes.
Complying with its obligations, the plaintiff
applied for a guarantee and
contracted with another foundry to cast the copper shoes. Since it had some
financial and cash flow
problems, the plaintiff's holding company ("TCI" for
short) made all these payments before summons was issued. In the absence of
a
"formal" agreement and book entries to reflect a debt between the plaintiff and
TCI and since TCI had written off the debt for
tax purposes, the defendant
argued that the plaintiff had failed to prove that it had a legal obligation to
repay TCI and that without
such an obligation the plaintiff cannot be said to
have suffered damages. The trial judge accepted the notion that a legal
obligation
to repay TCI had to be shown but concluded that there was a tacit
agreement to repay TCI whenever the plaintiff was able to do so.
[11] The
plaintiff and TCI, the evidence disclosed, in conducting their business, tended
to disregard their respective corporate
identities. Employees of the one worked
for and acted on the behalf of the other whenever it suited their business. It
was not even
always clear in whose employ a particular individual was. In
negotiating with CMI, the legendary corporate veil was discarded.
Whether TCI
paid as agent, negotiorum gestor or as donor, it paid the
plaintiff's debt. The plaintiff suffered its loss when the breach occurred and
was entitled to be recompensed
by the defendant, and the fact that TCI had paid
is at best a collateral benefit. (Hunter v Shapiro 1955 (3) SA 28 (D);
Sandown Park (Pty) Ltd v Hunter Your Wine & Spirit Merchant (Pty) Ltd and
another 1985 (1) SA 248 (W)). The defendant's counsel, correctly in my
view, did not attempt to support the trial court's reasoning to the contrary.
[12] Loss of management time in the other head of damages in contention.
Forbes J in Tate & Lyle Food and Distribution Ltd v Greater London
Council and another [1981] 3 All ER 716 (QBD) accepted the proposition that
the loss of managerial time which otherwise might have been engaged in the
trading activities
of a concern and which had to be deployed in managing the
consequences of a wrongful act (in that case a tort) can be claimed as
a head of
damages, provided the loss can be quantified. As a general proposition this
must be correct. But there must be at least
some evidence that the managers
would have expended their time on one or other income generating venture, and
that managing the consequences
of the wrong was not simply dealt within the
ordinary course of their duties.
[13] Witnesses for the plaintiff analysed
the time spent in investigating the reasons for the failure of the shoes, the
best means
of correcting the problem and in making good the defendant's default.
Because the plaintiff is in the business of selling the time
and services of its
employees, it was able to prove the cost to it for every hour spent by each
individual employee. The trial court,
in its calculation, deducted the profit
element because the warranty clause quoted in par [6] above, excluded claims for
loss of
profit.
[14] Due recognition must be given to the fact that it is
extremely difficult to prove damages such as these and that in assessing
the
sufficiency of the evidence "a fairly robust approach" may be adopted
(Thompson v Scholtz [1998] ZASCA 87; 1999 (1) SA 232 (SCA) 249B).
[15] During his
evidence in chief, the plaintiff's witness, Wilson, testified that there was a
loss for the plaintiff because "if
there was no problem with the contact shoes
we would not have to do that and that is time lost to us." He conceded during
cross-examination
that the cost to the company of, say, his salary did not
change because that cost was a constant. This evidence did not address
the
issue. However, Smidt, the chief executive officer of the plaintiff gave the
following evidence:
"There is one suggestion which was made, and I would like you to deal with it, to Mr Wilson, namely that if one has regard to EXHIBIT M it was suggested that these employees of the plaintiff, including yourself and Mr Wilson, were paid their salaries by the plaintiff in any event, whether they were busy dealing with contact shoes problems or any other problems and therefore plaintiff cannot suggest that time spent on the contact shoe problem constitutes a loss to the plaintiff. — I think that presupposes that our people would otherwise have stood doing nothing and would not be recovered in other areas. I think if you accept that, generally speaking, a large proportion of our income is derived from recovery and sale of man hours it does not really hold true. I think had they not been working in this area they would have been working elsewhere in a recoverable manner."
Smidt was not cross-examined on the
issue and the matter was left somewhat in the air. Since there is nothing to
gainsay the slightly
tentative evidence and taking less than a robust view of
the matter, I believe that the evidence suffices to establish as a probability
that the time spent would otherwise have been utilized gainfully, especially in
view of the nature of the plaintiff's business.
[16] Turning ultimately to
the question of costs, Heher J ordered the defendant to pay costs on the scale
as between attorney and
own client. Because I am of the view
that the judge misdirected himself on a number of aspects relating to costs, it
becomes necessary
to deal in some detail with his findings relative to the
issue.
[17] The defendant's witness, Smith, gave false evidence relating to
the question whether the quality control plan accompanied the
quotation.
However, to hold that this issue was the "real dispute" in the case and that but
for it the case would have been substantially
shortened in my view overstates
the position. Counsel's submission that the dispute did not contribute more
than 10% to the case
is closer to the mark. Dishonesty on one of a large number
of issues does not usually justify a special order as to costs in relation
to
the whole of the case, including the expensive technical evidence which was
triggered by the allegations made by the plaintiff
in its particulars of claim,
superfluously as it transpired in the end. For example, of the six warranties
relied upon, the plaintiff
eventually abandoned five, and of the eight breaches
it succeeded on one.
[18] Another pebble in the judicial shoe was the
defendant's "ill-judged attempt to obstruct the course of justice." Seven
instances
were enumerated where the defendant had refused to make requested
admissions; some of the refusals were found to have been without
a bona
fide basis, unnecessary, without substance, vexatious or opportunistic.
Except in one instance, the disputed items became common cause
or did not take
up more than a page or two of evidence. The exception relates to an admission
on quantum or aspects of quantum.
Although the behaviour of the defendant was
irritating and somewhat obstructive, it succeeded to reduce the quantum from
about R480
000 to R400 000. The fact is, the plaintiff would probably have been
absolved from the instance if it was not permitted to reopen
its case to present
evidence on damages during argument. Once again, in the context of the case as
a whole, the defendant's recalcitrant
behaviour on this aspect did not
substantially increase the costs. It is noteworthy that the trial judge, in
dealing with the refusal
to admit quantum did not brand the defendant's
behaviour with any deprecatory epithet or adjective.
[19] The final
complaint about the defendant's conduct relates to the fact that despite
requests from the plaintiff, the defendant's
expert failed to attend a pre-trial
conference with the plaintiff's new expert. A meeting had been held with the
plaintiff's former
expert, but it produced nothing of consequence. Having read
and reread the expert evidence, I am unable to envisage how the litigation
would
have been curtailed by a meeting. The scientific battle lines were clearly
drawn and each stuck to his own gun. In any event,
it was within the province
of the trial judge to have ordered a conference during the trial, something that
was not done.
[20] To sum up, in considering a punitive costs order a court
should warn itself against using hindsight in assessing the conduct
of a party.
The defendant had an eminent expert who gave an opinion based upon experimental
data which was not controverted and
was entitled to rely thereon. Its defences
were substantial although in retrospect misconceived. Even the trial judge by
granting
leave to appeal thought that there was a reasonable prospect of success
on appeal. The learned judge did refer to authorities that
hold that dishonesty
in the proceedings and presenting false evidence are grounds for awarding costs
on the attorney and client scale
but the quantum leap to the "own" portion was
not explained. Although invited to deal with the difference between the two
types
of attorney and client costs, but not having had the advantage of full
argument, I wish to say as little as possible. It has become
notable that a
practice has taken roots in some jurisdictions of making awards of costs on an
attorney and own client scale where
someone other than the own client or his
privy is involved. Whether such orders are justified or justifiable in the
light of decisions
of this Court (such as Nel v Waterberg Landbouwers
Ko-operatiewe Vereeniging 1946 AD 597) may to be questioned. Further, sight
appears to be lost of the fact that they may have unexpected or unforeseeable
consequences
(Cambridge Plan AG v Cambridge Diet (Pty) Ltd and Others
1990 (2) SA 574 (T)).
[21] Having identified a number of material
misdirections, this Court is entitled to exercise its own discretion. Because
there
is nothing special about the defendant's conduct, excepting Smith's
dishonesty, which deserves the severe opprobrium of a special
costs order in
this case, costs ought to be on a party and party scale. It is not feasible to
isolate the costs caused by the dishonesty
in order to make a special award in
that regard. The defendant's limited success on appeal cannot carry the costs
of appeal. The
employment of two counsel by the plaintiff for purpose of the
appeal, on the other hand, was fully justified having regard to the
nature and
scope of the appeal.
The following order is made:
(a) The appeal is upheld to the extent only that par 4 of the order of the court a quo is amended to read: "Costs of suit as between party and party."
(b) The appeal is otherwise dismissed with costs, including the costs of two counsel.
_____________________
L T C HARMS
JUDGE OF APPEAL
Agree:
GROSSKOPF JA
ZULMAN JA
MELUNSKY
AJA
MPATI AJA
[1]Its final outcome is reported: Titaco Projects (Pty) Ltd v A A Alloy Foundry (Pty) Ltd 1996 (3) SA 320 (W).